Small updates from the field, written the way we'd tell you in person. Nothing here needs a reply — just a way to keep you close to the work.

Thursday, Dec 4
Marcus, site lead

Cabinet installation was completed today. Electrical rough-ins are now finished, and we're preparing for countertop templating next week. Site is buttoned up for the weekend.

Tuesday, Dec 2
Ellie, lead designer

Walked the space this morning. The oak looks even softer in person than in the samples — you're going to love it. Sending an updated hardware photo once brass arrives.

Friday, Nov 28
Marcus, site lead

Countertop templater is scheduled for Dec 10. No action needed from you — we'll be on-site to walk them through the layout.

Wednesday, Nov 26
Ellie, lead designer

Small note: we're recommending we swap the pantry pulls for a slightly slimmer profile. I'll add options to Selections for your take — nothing urgent.